Before a house could be built it was necessary to mark the location of
the foundations: "the setting out". To locate their correct position,
the builders used planks and painted the intended thickness of the walls
onto the planks. Then the trenches were dug for the foundation. The
weight of the house had to be evenly distributed over the ground area
otherwise construction faults could occur through subsidence. This is
particularly the case in Amsterdam because of the high level of the
ground water and the peaty soil. The solution was to drive long piles
into the ground until they reached the sandplates at a depth of 40 to
60 feet. This was achieved by manpower.
For the
foundation of the wall pairs of piles were driven into the
ground 80 cm apart, until the length of the house was completed.
The tops of the
piles were sawn level, and fastened together by nailing heavy
wooden planks on top of them with iron or wooden nails.
The wooden foundation had to be kept submerged beneath the ground
water level to stop the rotting process setting in, and thus avoiding
subsidence.
Illustration
from:
"De Beijekorf des Gemoeds"
Jan Luijken (1709)
The brickwork
The wooden foundation formed the base for the brick foundation. A brick
wedge-shaped structure of about five layers was built on top of the
foundation planks; the base being broader than the top. Three kinds of
mortar were used. The layers in the "wedge" had a loam mixture between
them. The brickwork above the wedge had a chalk or lime mortar, and a
hard mortar, consisting of sand, chalk and trass was used in the five or
six layers above and below ground level. A harder brick was used here
forming a damp course to stop the ground water seeping up into the house
causing rising damp.
The bricklayer
ensured the bricks were laid horizontally and at right angles by
using a tape attached to stakes, with measurements marked for
the height of each layer and a plummet.
The carpentry
Only after the bricklayer had completed the cellar walls could the
carpenter start to work on the cellar ceiling. The pine beams were
anchored into the wall. A temporary work floor was placed on top of the
floor beams so that the bricklayer could continue building the sidewalls
until he reached the correct height for the next floor.
This process
was repeated until the right number of floors had been
completed.
The ends of the beams were sealed with tar to stop them rotting. The
wall anchors kept the beams securely attached in the wall and also
stopped the wall from buckling.
The roof
Only after the
appropriate number of floors had been achieved and the parapet
was at the right height could the carpenter start on the roof.
The roof structure had to be extremely sturdy. This was achieved
by using a system of triangles called trusses. A truss consists
of a post and beam construction.
A curved brace
was placed between the post and the collar beam to stop the
structure from swaying. The beams were attached together by
using a mortise and tenon fastening with wooden pegs of
approximately an inch thickness.
Then the roof trusses were placed in the correct position and
attached to the garret beams. The apex had to be placed before the
rafters, tilelathes and tiles could be fitted. Finally the roof tiles
were laid and were sealed on the inside with a mortar made from sand,
chalk, and pigs' or horsehair. A hoisting beam was attached to two extra
collar beams at the front of the house to raise and lower goods and
furniture. Lead coated gutters and drainpipes were placed at an angle
leading off to the back of the house to catch the rainwater.
Building the front and back facade
The front and back facades were completed last. Scaffolding was placed
at the front and the back of the house. The bricklayer and the carpenter
had to work together to mark out the location of the doors and windows.
The carpenter then made the frames for the doors and windows, so the
bricklayer could complete the facades. Meanwhile, the carpenter could
make the windows and doors.
The facades
were built at an angle leaning slightly forward to keep the rain
off. The old wooden houses were also built in this way. The top
floors protruded more than the bottom ones so that the rain ran
off the facade without soaking it.
Brick houses were also made waterproof by filling the joins between
the bricks with a high quality mortar that was water resistant.
The decorations
A decorative
gable was placed at the top of the facade for the finishing
touch. The stonemason made a specially carved sandstone
frontispiece and shoulder pieces.
These elements were painted a creamy colour called "Bentheim yellow"
because sandstone has the tendency to turn black.